Press Release- For Immediate Release
December 18, 2025
Montgomery County Precinct 4 Announces Flood Mitigation Grant Plan
Commissioner Gray and Montgomery County Precinct 4 held a public meeting last week to showcase the Montgomery County Precinct 4 Flood Mitigation Grant Plan, one of the many efforts focused on reducing flood risk and improving community resilience across Precinct 4. This effort is supported through grant funding awarded under FEMA’s Flood Mitigation Assistance (FMA) Program, administered by the Texas Water Development Board (TWDB). The FMA Program provides funding to help communities reduce or eliminate the risk of repetitive flood damage to structures insured by the National Flood Insurance Program (NFIP).
Study began in September 2024 and will conclude in December 2025 with a finalized Study Report with recommended projects & BCRs (benefit-cost ratios). Projects must show measurable benefits and cost savings to qualify for FEMA funding. BCR compares the estimated benefits of a project (i.e. reduced flood damages and avoided repair costs) to its total cost. If the BCR is greater than 1.0, the project’s benefits outweigh its costs, thus eligible for FEMA funding. If the BCR is less than 1.0, costs are higher than the expected benefits, thus not qualified for FEMA funding. This Study was completed by Cascade Civil Services, selected through the competitive Request For Qualifications process.
Project identification methodology:
- BCR greater than 1.0 (calculated using FEMA benefit-cost tool)
- Structures with repetitive flood loss within project area, identified through previous FEMA claims
- Project areas not located within a floodplain
- Precinct-identified locations that have drainage issues, determined by both staff in the field & calls/emails received from residents
This is Step 1 of Precinct 4’s Flood Mitigation Grant Plan. Based on the project identification methodology, 15 proposed locations were selected of the 43 evaluated locations that are in need of drainage improvements and also qualify for grant funding through the FMA Program. The total estimated investment would bring $53 million to Precinct 4, benefitting an estimated 440 homes.
Precinct 4 will submit one project per federal grant cycle for funding through FEMA’s Flood Mitigation Assistance (FMA) Program, anticipated yearly. Once FEMA grant funding is approved, the projects will enter final design, permitting & construction. The estimated time to complete this Flood Mitigation Grant Plan is approximately 20 years, and aligns with Precinct 4’s overall 20-Year Drainage Plan. The proposed projects identified will support the ongoing drainage improvements that Precinct 4 is continuously working on.
| Neighborhood | Project | Benefits | Benefit-Cost Ratio | Number of Structured Benefitted |
| Deer Trail Two-Section 2 | Add new enclosed storm sewer systems to improve drainage and lower water levels up to 2.5 ft.
Construct a drainage swale to convey stormwater flows not contained within the proposed 60” trunkline system. |
$4.14
million |
1.09 | 61 |
| Deer Trail Two- Section 4 | Add new enclosed storm sewer systems to improve drainage and lower water levels up to 2.5 ft.
Construct a drainage swale to convey stormwater flows not contained within the proposed 60” trunkline system. |
$1.28
million |
1.04 | 17 |
| Golden Trails | Add new enclosed storm sewer systems to improve drainage and lower water levels up to 2.5 ft.
Construct a drainage swale to convey stormwater flows not contained within the proposed 60” trunkline system. |
$1.28
million |
1.04 | 17 |
| Heritage Oaks | Re-grade roadside ditches, replace driveway culverts and add new outfall channel. | $3.11 million | 1.56 | 91 |
| Lake Chateau Woods- Section 1 | Replace ditches with storm sewer and curb and gutter system.
Upgrade the drainage system to outfall through a new storm sewer to increase capacity and reduce localized flooding. |
$3.68
million |
1.32 | 17 |
| Oak Lane Acres | Construct new 100-foot wide interceptor channel to divert floodwaters away from homes. | $2.58 million | 1.42 | 12 |
| Oakley | Improve central drainage channel and extend culverts under E. Community Drive. | $9.92 million | 1.31 | 13 |
| River Club Estates | Replace ditches with 5’x2′ trunkline and upsized outfall to reduce flooding by over 2 feet. | $8.45 million | 2.58 | 9 |
| Shadowland Retreat | Add 36″ storm sewer and new 4’x2′ culvert to improve drainage and reduce flood depth by up to 2 feet. | $9.92 million | 2.69 | 13 |
| Summer Hills | Convert open channel to 10’x4′-10×5′ trunkline and extend outfall to existing pond. | $2.88 million | 1.02 | 17 |
| Timberlane Acres- Section 7 | Replace central channel with storm sewer and re-grade roadside ditches. | $1.66 million | 1.07 | 40 |
| Virginia Estates | Install new 7’x3′-6’x5′ trunkline connecting to the Woodridge Stormwater Detention Basin. | $4.05 million | 1.03 | 44 |
| Whispering Pines | Convert north-south drainage ditch into enclosed 10’x3’ trunkline to relieve neighborhood flooding.
Upgrades to the north–south drainage system will extend about 4,110 feet and are expected to reduce 10-year water levels by up to 1.5 feet and 100-year levels by up to 1 foot. |
$9.19
million |
1.23 | 74 |
| White Oak Plantation | Extend storm sewer and add new 9.5-acre-foot detention pond for stormwater storage.
Proposed improvements will increase stormwater capacity and reduce 10-year water surface elevations by 0.25–0.5 feet within the subdivision. |
$9.92
million |
1.20 | 13 |
| Woodway Forest | Upgrade storm sewer with dual 10’x4′ box culverts and re-grade outfall channel. | $7.51 million | 1.49 | 18 |





